| Action Date | Action Description |
|---|---|
| HPHC Review Pending | |
| Biologist Report | |
| Jan 19, 2022 | Assent Application Received |
| Jan 20, 2022 | Administrative Review for Completeness |
| Feb 10, 2022 | Bio Team Review for Completeness |
| Feb 10, 2022 | Application Accepted |
| Feb 11, 2022 | Project Manager |
| Sep 08, 2023 | HPHC Historical Preservation No Effect |
| Nov 21, 2023 | Biologist Report |
| Nov 22, 2023 | Typist for Processing |
| Nov 22, 2023 | Executive Sign Off |
| Nov 22, 2023 | Sent to Photo Copy |
| Nov 22, 2023 | Permit Approved |
| Nov 23, 2023 | Permit Mailed |
| Dec 27, 2023 | Land Evidence Date |
| Sep 10, 2025 | Modification Request |
| Sep 12, 2025 | Administrative Review for Completeness |
| Sep 29, 2025 | Bio Team Review for Completeness |
| Sep 29, 2025 | Project Manager |
| Sep 29, 2025 | Application Accepted |