| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Dec 12, 2022 | Assent Application Received |
| Dec 16, 2022 | Administrative Review for Completeness |
| Dec 16, 2022 | Bio Team Review for Completeness |
| Dec 16, 2022 | Application Accepted |
| Dec 16, 2022 | Project Manager |
| Dec 16, 2022 | Category A* (Docks) |
| Jan 10, 2023 | HPHC Historical Preservation No Effect |
| Mar 13, 2023 | Additional Information Received |
| Mar 29, 2023 | 30 day Public Notice Issued |
| Apr 27, 2023 | Objections/Comments Received |
| Apr 28, 2023 | Public Notice End Date |
| May 03, 2023 | Objections/Comments Received |
| May 25, 2023 | Objections/Comments Received |
| May 28, 2023 | Public Notice End Date Extension Granted |
| May 30, 2023 | Objections/Comments Received |
| Jun 14, 2023 | Mail Agenda Notice |
| Jun 19, 2023 | Biologist Report |
| Jun 21, 2023 | Supervisor Biologist SignOff |
| Jun 22, 2023 | Supervisor Engineer SignOff |
| Jun 22, 2023 | Executive Signoff of Staff Reports |
| Jun 27, 2023 | Council Approval Granted |
| Jun 27, 2023 | Semi-Monthly Meeting Date Scheduled |
| Jul 03, 2023 | Additional Information Received |
| Jul 20, 2023 | Plans Received |
| Oct 04, 2023 | Legal Response/Decision |
| Nov 08, 2023 | Stipulation Package from Biologist |
| Nov 09, 2023 | Typist for Processing |
| Nov 09, 2023 | Executive Sign Off |
| Nov 09, 2023 | Sent to Photo Copy |
| Nov 09, 2023 | Permit Approved |
| Nov 14, 2023 | Permit Mailed |
| Dec 05, 2023 | Land Evidence Date |
| Aug 27, 2024 | Commencement of Work Notice received |