| Action Date | Action Description |
|---|---|
| Jun 26, 2023 | CHA Worksheet received |
| Jun 26, 2023 | Assent Application Received |
| Jun 30, 2023 | Administrative Review for Completeness |
| Jul 05, 2023 | Bio Team Review for Completeness |
| Jul 05, 2023 | Deficient Application - Owner Notification Sent |
| Aug 04, 2023 | Deficiency Response Received |
| Aug 08, 2023 | Bio Team Review for Completeness |
| Aug 08, 2023 | Application Accepted |
| Aug 08, 2023 | Project Manager |
| Aug 31, 2023 | Biologist Report |
| Sep 11, 2023 | HPHC Historical Preservation No Effect |
| Sep 12, 2023 | Typist for Processing |
| Sep 12, 2023 | Executive Sign Off |
| Sep 12, 2023 | Sent to Photo Copy |
| Sep 12, 2023 | Permit Approved |
| Sep 18, 2023 | Permit Mailed |
| Oct 13, 2023 | Land Evidence Date |
| Oct 07, 2024 | Additional Information Received |
| Oct 07, 2024 | Assent Requirement |