| Action Date | Action Description | 
|---|---|
| Feb 11, 2005 | Assent Application Received | 
| Feb 15, 2005 | Administrative Review for Completeness | 
| Feb 23, 2005 | Deficient Application - Owner Notification Sent | 
| Mar 08, 2005 | Deficient Application Picked Up | 
| Mar 31, 2005 | Deficiency Response Received | 
| Apr 11, 2005 | Deficient Application Picked Up | 
| Apr 28, 2005 | Deficiency Response Received | 
| May 02, 2005 | Team Review for Completeness | 
| May 02, 2005 | Application Accepted | 
| May 02, 2005 | Category B assigned | 
| May 17, 2005 | 30 day Public Notice Issued | 
| Jul 15, 2005 | Correspondence Received | 
| Jul 15, 2005 | Correspondence Received | 
| Jul 20, 2005 | Public Notice End Date | 
| Jul 21, 2005 | HPHC Review Pending | 
| Jul 26, 2005 | Historical Preservation Approval Granted | 
| Aug 26, 2005 | Plans Received | 
| Sep 08, 2005 | Water Quality Certification | 
| Oct 04, 2005 | Biologist Report | 
| Oct 04, 2005 | Engineering Report | 
| Oct 06, 2005 | Plans Received | 
| Oct 07, 2005 | Plans Received | 
| Oct 11, 2005 | Supervisor Biologist SignOff | 
| Oct 11, 2005 | Supervisor Engineer SignOff | 
| Oct 12, 2005 | Executive Sign Off | 
| Oct 19, 2005 | Ready to Schedule Semi-Monthly Meeting | 
| Oct 19, 2005 | Mail Agenda Notice | 
| Oct 25, 2005 | Semi-Monthly Meeting Held | 
| Oct 25, 2005 | Council Approval Granted | 
| Oct 25, 2005 | Semi-Monthly Meeting Date Scheduled | 
| Nov 29, 2005 | Legal Response/Decision | 
| Dec 06, 2005 | Permit Approved | 
| Dec 06, 2005 | Stipulation Package from Biologist | 
| Dec 06, 2005 | Stipulation Package by Engineer | 
| Dec 06, 2005 | Typist for Processing | 
| Dec 06, 2005 | Executive Sign Off | 
| Dec 14, 2005 | Sent to Photo Copy | 
| Dec 14, 2005 | Chairman's Signoff |