| Action Date | Action Description |
|---|---|
| Feb 15, 2005 | Assent Application Received |
| Feb 17, 2005 | Administrative Review for Completeness |
| Feb 21, 2005 | Team Review for Completeness |
| Feb 21, 2005 | Application Accepted |
| Feb 24, 2005 | 30 day Public Notice Issued |
| Mar 01, 2005 | HPHC Review Pending |
| Mar 17, 2005 | Correspondence Received |
| Mar 24, 2005 | Engineering Report |
| Mar 24, 2005 | Biologist Report |
| Mar 24, 2005 | Supervisor Biologist SignOff |
| Mar 24, 2005 | Supervisor Engineer SignOff |
| Mar 28, 2005 | Executive Sign Off |
| Apr 15, 2005 | Ready to Schedule Semi-Monthly Meeting |
| Apr 15, 2005 | Public Notice End Date |
| Apr 15, 2005 | Mail Agenda Notice |
| Apr 18, 2005 | Correspondence Received |
| Apr 25, 2005 | US Army Corp of Engineers Permit Date |
| Apr 26, 2005 | Semi-Monthly Meeting Held |
| Apr 26, 2005 | Council Approval Granted |
| Apr 26, 2005 | Semi-Monthly Meeting Date Scheduled |
| Apr 27, 2005 | US Army Corps of Engineers Approval Received |
| May 02, 2005 | Stipulation Package from Biologist |
| May 02, 2005 | Stipulation Package by Engineer |
| May 02, 2005 | Category B assigned |
| May 04, 2005 | Typist for Processing |
| May 04, 2005 | Sent to Photo Copy |
| May 04, 2005 | Executive Sign Off |
| May 04, 2005 | Permit Approved |
| May 06, 2005 | Biologist Report |
| May 09, 2005 | Legal Response/Decision |
| May 10, 2005 | US Army Corp of Engineers Permit Date |
| May 11, 2005 | US Army Corps of Engineers Approval Received |