| Action Date | Action Description |
|---|---|
| Apr 04, 2005 | Assent Application Received |
| Apr 05, 2005 | Administrative Review for Completeness |
| Apr 15, 2005 | Additional Information Received |
| Apr 21, 2005 | Team Review for Completeness |
| Apr 21, 2005 | Application Accepted |
| May 03, 2005 | HPHC Review Pending |
| Jun 14, 2005 | Engineering Report |
| Jun 16, 2005 | Typist for Processing |
| Jun 16, 2005 | Executive Sign Off |
| Jun 16, 2005 | Sent to Photo Copy |
| Jun 16, 2005 | Permit Approved |
| Jun 28, 2005 | Land Evidence Date |