| Action Date | Action Description |
|---|---|
| Jul 17, 2008 | Assent Application Received |
| Jul 18, 2008 | Administrative Review for Completeness |
| Jul 22, 2008 | Team Review for Completeness |
| Jul 22, 2008 | Team Review for Completeness |
| Jul 22, 2008 | Application Accepted |
| Jul 22, 2008 | Category A* (Docks) |
| Aug 01, 2008 | HPHC Historical Preservation No Effect |
| Nov 28, 2008 | 30 day Public Notice Issued |
| Dec 28, 2008 | Public Notice End Date |
| Jan 08, 2009 | Engineering Report |
| Jan 15, 2009 | Dock Meeting -- Approval |
| Jan 16, 2009 | US Army Corp of Engineers Permit Date |
| Jan 22, 2009 | US Army Corps of Engineers Approval Received |
| Jan 27, 2009 | Typist for Processing |
| Jan 27, 2009 | Executive Sign Off |
| Jan 27, 2009 | Sent to Photo Copy |
| Jan 27, 2009 | Permit Approved |
| Mar 16, 2009 | Land Evidence Date |
| Jun 14, 2013 | Extension Toll letter mailed |