| Action Date | Action Description |
|---|---|
| Oct 05, 2009 | Assent Application Received |
| Oct 05, 2009 | Administrative Review for Completeness |
| Oct 06, 2009 | Team Review for Completeness |
| Oct 06, 2009 | Team Review for Completeness |
| Oct 06, 2009 | Application Accepted |
| Nov 09, 2009 | HPHC Historical Preservation No Effect |
| Nov 24, 2009 | 30 day Public Notice Issued |
| Dec 18, 2009 | Correspondence Received |
| Dec 24, 2009 | Public Notice End Date |
| Jan 12, 2010 | Biologist Report |
| Jan 12, 2010 | Engineering Report |
| Jan 13, 2010 | Typist for Processing |
| Jan 13, 2010 | Permit Approved |
| Jan 13, 2010 | Executive Sign Off |
| Jan 13, 2010 | Sent to Photo Copy |
| Jun 22, 2010 | Duplicate Original Assent requested/mailed |
| Jun 28, 2010 | Land Evidence Date |