| Action Date | Action Description |
|---|---|
| Jan 05, 2011 | Assent Application Received |
| Jan 05, 2011 | Administrative Review for Completeness |
| Jan 11, 2011 | Team Review for Completeness |
| Jan 11, 2011 | Team Review for Completeness |
| Jan 11, 2011 | Application Accepted |
| Jan 26, 2011 | HPHC Historical Preservation No Effect |
| Feb 01, 2011 | 30 day Public Notice Issued |
| Mar 01, 2011 | Public Notice End Date |
| Apr 08, 2011 | US Army Corps of Engineers Approval Received |
| Apr 19, 2011 | Engineering Report |
| Apr 21, 2011 | Biologist Report |
| Apr 22, 2011 | Executive Signoff of Staff Reports |
| May 11, 2011 | Ready to Schedule Semi-Monthly Meeting |
| May 11, 2011 | Mail Agenda Notice |
| May 17, 2011 | Objections/Comments Received |
| May 24, 2011 | Council Approval Granted |
| May 24, 2011 | Semi-Monthly Meeting Held |
| May 24, 2011 | Semi-Monthly Meeting Date Scheduled |
| Jun 06, 2011 | Additional Information Received |
| Jun 06, 2011 | Stipulation Package from Biologist |
| Jun 06, 2011 | Stipulation Package by Engineer |
| Jun 07, 2011 | Legal Response/Decision |
| Jun 14, 2011 | Under Review/Decision |
| Jun 14, 2011 | Typist for Processing |
| Jun 14, 2011 | Permit Approved |
| Jun 15, 2011 | Executive Sign Off |
| Jun 15, 2011 | Sent to Photo Copy |
| Dec 02, 2011 | Land Evidence Date |