| Action Date | Action Description |
|---|---|
| Monitoring Report | |
| Mar 09, 2011 | Assent Application Received |
| Mar 10, 2011 | Administrative Review for Completeness |
| Mar 29, 2011 | Team Review for Completeness |
| Mar 29, 2011 | Team Review for Completeness |
| Mar 29, 2011 | Application Accepted |
| Apr 08, 2011 | HPHC Historical Preservation No Effect |
| Apr 20, 2011 | 30 day Public Notice Issued |
| May 20, 2011 | Public Notice End Date |
| May 20, 2011 | Additional Information Received |
| Jul 08, 2011 | Additional Information Received |
| Jul 11, 2011 | Additional Information Received |
| Jul 14, 2011 | Additional Information Received |
| Jul 15, 2011 | Plans Received |
| Jul 18, 2011 | Additional Information Received |
| Jul 19, 2011 | Objections/Comments Received |
| Jul 19, 2011 | Biologist Report |
| Jul 19, 2011 | Engineering Report |
| Jul 19, 2011 | Supervisor Biologist SignOff |
| Jul 19, 2011 | Supervisor Engineer SignOff |
| Jul 20, 2011 | Executive Signoff of Staff Reports |
| Jul 20, 2011 | Ready to Schedule Semi-Monthly Meeting |
| Jul 20, 2011 | Mail Agenda Notice |
| Jul 26, 2011 | Council Approval Granted |
| Jul 26, 2011 | Semi-Monthly Meeting Held |
| Jul 26, 2011 | Semi-Monthly Meeting Date Scheduled |
| Aug 04, 2011 | Plans Received |
| Aug 04, 2011 | Legal Response/Decision |
| Aug 18, 2011 | Land Evidence Date |
| Aug 18, 2011 | Water Quality Certification |
| Aug 18, 2011 | Stipulation Package from Biologist |
| Aug 18, 2011 | Stipulation Package by Engineer |
| Aug 19, 2011 | Typist for Processing |
| Aug 19, 2011 | Executive Sign Off |
| Aug 19, 2011 | Sent to Photo Copy |
| Aug 19, 2011 | Permit Approved |
| Aug 24, 2011 | Monitoring Report |
| Aug 30, 2011 | Land Evidence Date |
| Aug 31, 2011 | Commencement of Work Notice received |