| Action Date | Action Description |
|---|---|
| Dec 21, 2011 | Assent Application Received |
| Dec 22, 2011 | Administrative Review for Completeness |
| Dec 22, 2011 | Team Review for Completeness |
| Dec 22, 2011 | Team Review for Completeness |
| Dec 22, 2011 | Application Accepted |
| Jan 04, 2012 | 30 day Public Notice Issued |
| Jan 04, 2012 | HPHC Historical Preservation No Effect |
| Feb 04, 2012 | Public Notice End Date |
| Mar 15, 2012 | Correspondence Received |
| Mar 16, 2012 | Public Notice End Date Extension Granted |
| Jan 02, 2014 | Biologist Report |
| Jan 02, 2014 | Engineering Report |
| Jan 07, 2014 | Typist for Processing |
| Jan 07, 2014 | Executive Sign Off |
| Jan 07, 2014 | Sent to Photo Copy |
| Jan 07, 2014 | Permit Approved |
| Jan 31, 2014 | Land Evidence Date |