| Action Date | Action Description |
|---|---|
| Feb 22, 2012 | Assent Application Received |
| Feb 23, 2012 | Administrative Review for Completeness |
| Feb 28, 2012 | Team Review for Completeness |
| Feb 28, 2012 | Team Review for Completeness |
| Feb 28, 2012 | Application Accepted |
| Aug 01, 2012 | Biologist Report |
| Aug 01, 2012 | Engineering Report |
| Aug 08, 2012 | Typist for Processing |
| Aug 08, 2012 | Executive Sign Off |
| Aug 08, 2012 | Sent to Photo Copy |
| Aug 08, 2012 | Permit Approved |
| Aug 14, 2012 | Land Evidence Date |
| May 04, 2018 | Note to File |