| Action Date | Action Description | 
|---|---|
| Aug 21, 2012 | Assent Application Received | 
| Aug 22, 2012 | Administrative Review for Completeness | 
| Aug 22, 2012 | Team Review for Completeness | 
| Aug 22, 2012 | Team Review for Completeness | 
| Aug 22, 2012 | Application Accepted | 
| Aug 24, 2012 | Biologist Report | 
| Aug 24, 2012 | Engineering Report | 
| Aug 30, 2012 | Typist for Processing | 
| Aug 30, 2012 | Permit Approved | 
| Sep 04, 2012 | Executive Sign Off | 
| Sep 04, 2012 | Sent to Photo Copy | 
| Sep 12, 2012 | HPHC Historical Preservation No Effect | 
| Sep 17, 2012 | Land Evidence Date |