| Action Date | Action Description |
|---|---|
| Sep 10, 2012 | Assent Application Received |
| Sep 11, 2012 | Administrative Review for Completeness |
| Sep 11, 2012 | Team Review for Completeness |
| Sep 11, 2012 | Team Review for Completeness |
| Sep 12, 2012 | Deficient Application - Owner Notification Sent |
| May 20, 2013 | Deficiency Response Received |
| Jun 05, 2013 | Team Review for Completeness |
| Jun 05, 2013 | Team Review for Completeness |
| Jun 05, 2013 | Deficient Application - Owner Notification Sent |
| Jun 21, 2013 | Application Accepted |
| Jun 21, 2013 | Finding of No Significant Impact-OTC |
| Oct 15, 2015 | Letter of Authorization |