| Action Date | Action Description |
|---|---|
| Mar 14, 2013 | Assent Application Received |
| Mar 15, 2013 | Administrative Review for Completeness |
| Mar 19, 2013 | Team Review for Completeness |
| Mar 19, 2013 | Application Accepted |
| Apr 01, 2013 | HPHC Historical Preservation No Effect |
| May 20, 2013 | Additional Information Received |
| Feb 21, 2014 | Additional Information Received |
| Jul 09, 2014 | Plans Received |
| Jul 21, 2014 | Plans Received |
| Sep 15, 2014 | Correspondence Received |
| Sep 17, 2014 | Biologist Report |
| Oct 02, 2014 | Permit Approved |
| Oct 03, 2014 | Typist for Processing |
| Oct 03, 2014 | Executive Sign Off |
| Oct 03, 2014 | Sent to Photo Copy |
| Nov 07, 2014 | US Army Corps of Engineers Approval Received |
| Sep 30, 2016 | Monitoring Report |
| Nov 18, 2016 | Commencement of Work Notice received |
| Dec 05, 2016 | Monitoring Report |
| Mar 03, 2017 | Monitoring Report |
| Jun 05, 2017 | Monitoring Report |
| Oct 25, 2017 | Monitoring Report |
| Jun 01, 2018 | Expiration of Assent/End of Tolling Legislation |
| Jun 22, 2018 | Monitoring Report |
| Feb 22, 2019 | Monitoring Report |
| Sep 16, 2020 | Monitoring Report |
| Jul 07, 2021 | Monitoring Report |
| Nov 17, 2022 | Monitoring Report |