| Action Date | Action Description |
|---|---|
| May 17, 2013 | Assent Application Received |
| May 17, 2013 | Administrative Review for Completeness |
| May 23, 2013 | Plans Received |
| Jun 05, 2013 | Deficient Application - Owner Notification Sent |
| Jun 05, 2013 | Team Review for Completeness |
| Jun 05, 2013 | Team Review for Completeness |
| Sep 19, 2013 | Deficiency Response Received |
| Sep 24, 2013 | Team Review for Completeness |
| Sep 24, 2013 | Application Accepted |
| Sep 30, 2013 | 30 day Public Notice Issued |
| Oct 29, 2013 | HPHC Historical Preservation No Effect |
| Oct 30, 2013 | Public Notice End Date |
| Oct 30, 2013 | Public Notice End Date Extension Granted |
| Nov 01, 2013 | Category B assigned |
| Nov 04, 2013 | Engineering Report |
| Nov 14, 2013 | Correspondence Received |
| Nov 14, 2013 | Biologist Report |
| Nov 15, 2013 | Executive Signoff of Staff Reports |
| Dec 13, 2013 | Objections/Comments Received |
| Dec 16, 2013 | US Army Corps of Engineers Approval Received |
| Jan 07, 2014 | Ready to Schedule Semi-Monthly Meeting |
| Jan 07, 2014 | Mail Agenda Notice |
| Jan 28, 2014 | Semi-Monthly Meeting Held |
| Jan 28, 2014 | Council Approval Granted |
| Jan 28, 2014 | Semi-Monthly Meeting Date Scheduled |
| Feb 18, 2014 | Legal Response/Decision |
| Feb 18, 2014 | 30 Day Appeal Notification to Owner |
| Feb 18, 2014 | Legal Response/Decision |
| Feb 18, 2014 | Under Review/Decision |
| Feb 24, 2014 | Stipulation Package from Biologist |
| Feb 24, 2014 | Stipulation Package by Engineer |
| Feb 25, 2014 | Typist for Processing |
| Feb 25, 2014 | Permit Approved |
| Feb 26, 2014 | Executive Sign Off |
| Feb 26, 2014 | Sent to Photo Copy |
| Mar 06, 2014 | Land Evidence Date |