| Action Date | Action Description |
|---|---|
| Dec 24, 2013 | Assent Application Received |
| Dec 24, 2013 | Administrative Review for Completeness |
| Dec 31, 2013 | Team Review for Completeness |
| Dec 31, 2013 | Application Accepted |
| Feb 20, 2014 | HPHC Historical Preservation No Effect |
| Feb 25, 2014 | Additional Information Received |
| Mar 07, 2014 | Plans Received |
| Apr 07, 2014 | Plans Received |
| Apr 14, 2014 | Biologist Report |
| Apr 29, 2014 | Typist for Processing |
| Apr 29, 2014 | Executive Sign Off |
| Apr 29, 2014 | Sent to Photo Copy |
| Apr 29, 2014 | Permit Approved |
| May 20, 2014 | Typist for Processing |
| May 20, 2014 | Typist for Processing |
| May 20, 2014 | Assent Correction Mailed |
| May 28, 2014 | Executive Sign Off |
| May 28, 2014 | Sent to Photo Copy |
| May 30, 2014 | Executive Sign Off |
| May 30, 2014 | Sent to Photo Copy |
| Jun 04, 2014 | Land Evidence Date |
| Oct 14, 2021 | Meeting Held |