| Action Date | Action Description |
|---|---|
| Dec 24, 2014 | Assent Application Received |
| Dec 24, 2014 | Administrative Review for Completeness |
| Jan 05, 2015 | Team Review for Completeness |
| Jan 05, 2015 | Application Accepted |
| Jan 05, 2015 | Category B assigned |
| Feb 06, 2015 | HPHC Historical Preservation No Effect |
| Apr 02, 2015 | Correspondence Received |
| Apr 06, 2015 | 30 day Public Notice Issued |
| May 06, 2015 | Public Notice End Date |
| May 13, 2015 | Note to File |
| Jul 10, 2015 | Plans Received |
| Jul 23, 2015 | Plans Received |
| Jul 24, 2015 | Engineering Report |
| Jul 24, 2015 | Biologist Report |
| Jul 24, 2015 | Supervisor Engineer SignOff |
| Jul 27, 2015 | Supervisor Biologist SignOff |
| Jul 28, 2015 | Executive Signoff of Staff Reports |
| Jul 28, 2015 | Special Exception Public Hearing Notice mailed |
| Sep 08, 2015 | Semi-Monthly Meeting Date Scheduled |
| Oct 13, 2015 | Semi-Monthly Meeting Date Scheduled |
| Oct 13, 2015 | Council Approval Granted |
| Oct 13, 2015 | Stipulation Package from Biologist |
| Oct 13, 2015 | Stipulation Package by Engineer |
| Oct 20, 2015 | Legal Response/Decision |
| Oct 20, 2015 | 30 Day Appeal Notification to Owner |
| Nov 30, 2015 | Typist for Processing |
| Dec 02, 2015 | Executive Sign Off |
| Dec 02, 2015 | Sent to Photo Copy |
| Dec 02, 2015 | Permit Approved |
| Apr 18, 2016 | Duplicate Original Assent requested/mailed |
| May 12, 2016 | Land Evidence Date |