| Action Date | Action Description |
|---|---|
| Oct 29, 2015 | Assent Application Received |
| Nov 02, 2015 | Administrative Review for Completeness |
| Nov 03, 2015 | Team Review for Completeness |
| Nov 09, 2015 | Deficient Application - Owner Notification Sent |
| Nov 16, 2015 | Deficient Application Picked Up |
| Nov 19, 2015 | Deficiency Response Received |
| Nov 23, 2015 | HPHC Historical Preservation No Effect |
| Nov 25, 2015 | Application Accepted |
| Nov 25, 2015 | Team Review for Completeness |
| Dec 10, 2015 | HPHC Historical Preservation No Effect |
| Dec 15, 2015 | 30 day Public Notice Issued |
| Dec 30, 2015 | Category A* (Docks) |
| Jan 25, 2016 | Biologist Report |
| Jan 26, 2016 | Typist for Processing |
| Jan 27, 2016 | Executive Sign Off |
| Jan 27, 2016 | Sent to Photo Copy |
| Jan 27, 2016 | Permit Approved |
| Feb 01, 2016 | Public Notice End Date Extension Granted |
| Feb 08, 2016 | Land Evidence Date |
| Feb 23, 2016 | US Army Corps of Engineers Approval Received |
| Mar 07, 2016 | Correspondence Received |