| Action Date | Action Description |
|---|---|
| Sep 27, 2017 | Assent Application Received |
| Sep 27, 2017 | Administrative Review for Completeness |
| Sep 29, 2017 | Team Review for Completeness |
| Sep 29, 2017 | Application Accepted |
| Sep 29, 2017 | Category B assigned |
| Oct 25, 2017 | HPHC Historical Preservation No Effect |
| Dec 18, 2017 | Additional Information Received |
| Jan 08, 2018 | 30 day Public Notice Issued |
| Feb 08, 2018 | Public Notice End Date |
| Feb 15, 2018 | Comments Received |
| Feb 16, 2018 | Engineering Report |
| Feb 16, 2018 | Public Notice End Date Extension Granted |
| Feb 16, 2018 | Mail Agenda Notice |
| Feb 20, 2018 | Executive Signoff of Staff Reports |
| Feb 20, 2018 | Biologist Report |
| Feb 27, 2018 | Council Approval Granted |
| Feb 27, 2018 | Semi-Monthly Meeting Date Scheduled |
| Mar 21, 2018 | Stipulation Package from Biologist |
| Mar 21, 2018 | Stipulation Package by Engineer |
| Mar 23, 2018 | Legal Response/Decision |
| Mar 23, 2018 | Typist for Processing |
| Mar 23, 2018 | Executive Sign Off |
| Mar 23, 2018 | Sent to Photo Copy |
| Mar 23, 2018 | Under Review/Decision |
| Mar 23, 2018 | Permit Approved |
| Apr 02, 2018 | US Army Corps of Engineers Approval Received |
| Apr 04, 2018 | Land Evidence Date |