| Action Date | Action Description |
|---|---|
| Feb 15, 2019 | Assent Application Received |
| Feb 15, 2019 | Administrative Review for Completeness |
| Feb 19, 2019 | Team Review for Completeness |
| Feb 19, 2019 | Application Accepted |
| Mar 13, 2019 | HPHC Review Pending |
| Mar 13, 2019 | HPHC Historical Preservation No Effect |
| Sep 10, 2019 | Plans Received |
| Sep 10, 2019 | Biologist Report |
| Sep 11, 2019 | Typist for Processing |
| Sep 11, 2019 | Executive Sign Off |
| Sep 11, 2019 | Sent to Photo Copy |
| Sep 11, 2019 | Permit Approved |
| Sep 23, 2019 | Land Evidence Date |
| Sep 15, 2021 | Modification Request |
| Sep 20, 2021 | Administrative Review for Completeness |
| Sep 21, 2021 | Bio Team Review for Completeness |
| Sep 23, 2021 | Project Manager |
| Oct 06, 2021 | Stipulation Package from Biologist |
| Oct 06, 2021 | Biologist Report |
| Oct 07, 2021 | Modification Approved |
| Oct 07, 2021 | Typist for Processing |
| Oct 07, 2021 | Executive Sign Off |
| Oct 07, 2021 | Sent to Photo Copy |
| Oct 08, 2021 | Permit Mailed |
| Oct 13, 2021 | HPHC Review Pending |
| Oct 13, 2021 | HPHC Historical Preservation No Effect |
| Oct 28, 2021 | Land Evidence Date |