| Action Date | Action Description |
|---|---|
| Mar 01, 2019 | Assent Application Received |
| Mar 01, 2019 | Administrative Review for Completeness |
| Mar 06, 2019 | Team Review for Completeness |
| Mar 06, 2019 | Application Accepted |
| Mar 06, 2019 | Category A* (Docks) |
| Mar 13, 2019 | 30 day Public Notice Issued |
| Mar 20, 2019 | HPHC Historical Preservation No Effect |
| Mar 20, 2019 | HPHC Review Pending |
| Apr 13, 2019 | Public Notice End Date |
| Jul 25, 2019 | Site Inspection |
| Jul 25, 2019 | Correspondence Received |
| Jul 25, 2019 | Site Inspection |
| Jul 30, 2019 | Correspondence Received |
| Jul 30, 2019 | Correspondence Received |
| Aug 02, 2019 | Correspondence Mailed/Faxed/E-mailed |
| Aug 02, 2019 | Meeting Held |
| Sep 05, 2019 | Correspondence Mailed/Faxed/E-mailed |
| Sep 09, 2019 | Phone Call |
| Sep 27, 2019 | Phone Call |
| Oct 22, 2019 | Phone Call |
| Feb 17, 2020 | Phone Call |
| Jun 12, 2020 | Additional Information Requested from Applicant |
| Aug 11, 2020 | 30-Day Notification of Cancellation letter |
| Sep 14, 2020 | Correspondence Received |
| Oct 22, 2020 | 30-Day Notification of Cancellation letter |
| Nov 17, 2020 | Correspondence Received |
| Nov 20, 2020 | Correspondence Mailed/Faxed/E-mailed |
| Dec 08, 2020 | Phone Call |
| Jan 04, 2021 | Correspondence Mailed/Faxed/E-mailed |
| Jan 04, 2021 | Correspondence Received |
| Feb 01, 2021 | Correspondence Received |
| Mar 15, 2021 | Note to File |
| Mar 18, 2021 | 30-Day Notification of Cancellation letter |
| Mar 22, 2021 | Application Cancelled |
| Mar 23, 2021 | Biologist Report |