| Action Date | Action Description |
|---|---|
| Jul 25, 2019 | Maintenance Certification Request |
| Jul 25, 2019 | Administrative Review for Completeness |
| Jul 29, 2019 | Team Review for Completeness |
| Jul 29, 2019 | Application Accepted |
| Jul 30, 2019 | Category A assigned |
| Jul 31, 2019 | Additional Information Requested from Applicant |
| Aug 07, 2019 | Additional Information Requested from Applicant |
| Aug 16, 2019 | HPHC Review Pending |
| Aug 16, 2019 | HPHC Historical Preservation No Effect |
| Sep 11, 2019 | Additional Information Received |
| Sep 12, 2019 | Additional Information Requested from Applicant |
| Sep 16, 2019 | Additional Information Received |
| Sep 16, 2019 | Letter of Authorization |
| Sep 18, 2019 | Plans Received |
| Oct 09, 2019 | Plans Received |
| Oct 11, 2019 | Biologist Report |
| Oct 11, 2019 | Typist for Processing |
| Oct 11, 2019 | Executive Sign Off |
| Oct 11, 2019 | Sent to Photo Copy |
| Oct 11, 2019 | Permit Approved |