| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Oct 16, 2019 | Assent Application Received |
| Oct 17, 2019 | Administrative Review for Completeness |
| Oct 18, 2019 | Bio Team Review for Completeness |
| Oct 21, 2019 | Deficient Application - Owner Notification Sent |
| Nov 14, 2019 | Deficiency Response Received |
| Nov 15, 2019 | Bio Team Review for Completeness |
| Nov 15, 2019 | Application Accepted |
| Nov 22, 2019 | HPHC Review Pending |
| Nov 22, 2019 | HPHC Historical Preservation No Effect |
| Dec 13, 2019 | Additional Information Requested from Applicant |
| Dec 16, 2019 | 30 day Public Notice Issued |
| Jan 13, 2020 | Objections/Comments Received |
| Jan 16, 2020 | Public Notice End Date |
| Feb 13, 2020 | Entry of Appearance Received |
| Feb 14, 2020 | US Army Corps of Engineers Approval Received |
| Mar 10, 2020 | Biologist Report |
| Mar 11, 2020 | Supervisor Biologist SignOff |
| Mar 11, 2020 | Supervisor Engineer SignOff |
| Mar 11, 2020 | Executive Signoff of Staff Reports |
| Apr 29, 2020 | Ready to Schedule Semi-Monthly Meeting |
| Apr 29, 2020 | Mail Agenda Notice |
| May 12, 2020 | Council Approval Granted |
| May 12, 2020 | Semi-Monthly Meeting Date Scheduled |
| Jun 23, 2020 | Legal Response/Decision |
| Jul 29, 2020 | Typist for Processing |
| Jul 29, 2020 | Executive Sign Off |
| Jul 29, 2020 | Sent to Photo Copy |
| Jul 29, 2020 | Permit Approved |
| Jul 29, 2020 | Stipulation Package from Biologist |
| Jul 29, 2020 | Category A* (Docks) |
| Aug 17, 2020 | Land Evidence Date |