| Action Date | Action Description |
|---|---|
| Nov 09, 2020 | Assent Application Received |
| Nov 10, 2020 | Administrative Review for Completeness |
| Nov 12, 2020 | Bio Team Review for Completeness |
| Nov 12, 2020 | Project Manager |
| Nov 12, 2020 | Application Accepted |
| Nov 25, 2020 | Category A* (Docks) |
| Nov 25, 2020 | HPHC Historical Preservation No Effect |
| Nov 25, 2020 | HPHC Review Pending |
| Jan 12, 2021 | US Army Corps of Engineers Approval Received |
| Aug 10, 2021 | Biologist Report |
| Aug 11, 2021 | Engineering Report |
| Aug 11, 2021 | 30-Day Notification of Cancellation letter |