| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| May 19, 2021 | Assent Application Received |
| May 20, 2021 | Administrative Review for Completeness |
| May 28, 2021 | Bio Team Review for Completeness |
| May 28, 2021 | Application Accepted |
| Jun 14, 2021 | Project Manager |
| Jun 28, 2021 | HPHC Review Pending |
| Jun 28, 2021 | HPHC Historical Preservation No Effect |
| Jul 19, 2021 | 30 day Public Notice Issued |
| Jul 21, 2021 | US Army Corps of Engineers Approval Received |
| Aug 19, 2021 | Public Notice End Date |
| Sep 01, 2021 | Biologist Report |
| Sep 01, 2021 | Stipulation Package from Biologist |
| Sep 01, 2021 | Typist for Processing |
| Sep 01, 2021 | Category A* (Docks) |
| Sep 01, 2021 | Executive Sign Off |
| Sep 01, 2021 | Sent to Photo Copy |
| Sep 01, 2021 | Permit Approved |
| Sep 03, 2021 | Permit Mailed |
| Sep 13, 2021 | Land Evidence Date |
| Jul 22, 2024 | Extension of Permit Request |
| Aug 21, 2025 | Enforcement Compliance Inspection Required |
| Aug 22, 2025 | Process Extension |
| Aug 22, 2025 | Extension Approved |