| Action Date | Action Description |
|---|---|
| Jul 19, 2021 | Assent Application Received |
| Jul 22, 2021 | Administrative Review for Completeness |
| Jul 28, 2021 | Bio Team Review for Completeness |
| Jul 28, 2021 | Deficient Application - Owner Notification Sent |
| Feb 09, 2022 | Deficiency Response Received |
| Feb 10, 2022 | Bio Team Review for Completeness |
| Feb 10, 2022 | Application Accepted |
| Feb 14, 2022 | Project Manager |
| Mar 02, 2022 | HPHC Review Pending |
| Mar 02, 2022 | HPHC Historical Preservation No Effect |
| Apr 07, 2022 | Additional Information Requested from Applicant |
| Aug 22, 2022 | 30-Day Notification of Cancellation letter |
| Nov 01, 2022 | Additional Information Received |
| Nov 14, 2022 | Additional Information Received |
| Nov 22, 2022 | Biologist Report |
| Nov 23, 2022 | Typist for Processing |
| Nov 23, 2022 | Executive Sign Off |
| Nov 23, 2022 | Sent to Photo Copy |
| Nov 23, 2022 | Permit Approved |
| Nov 25, 2022 | Permit Mailed |
| Jan 09, 2023 | Land Evidence Date |
| Nov 03, 2023 | Commencement of Work Notice received |