| Action Date | Action Description |
|---|---|
| Typist for Processing | |
| Aug 23, 2021 | Maintenance Certification Request |
| Aug 26, 2021 | Administrative Review for Completeness |
| Sep 01, 2021 | Eng Team Review for Completeness |
| Sep 07, 2021 | Deficient Application - Owner Notification Sent |
| Oct 01, 2021 | Deficiency Response Received |
| Oct 05, 2021 | Eng Team Review for Completeness |
| Nov 05, 2021 | Eng Team Review for Completeness |
| Nov 05, 2021 | Application Accepted |
| Nov 08, 2021 | Project Manager |
| Nov 23, 2021 | Correspondence Received |
| Dec 03, 2021 | HPHC Historical Preservation No Effect |
| Dec 03, 2021 | HPHC Review Pending |
| Dec 06, 2021 | 30 day Public Notice Issued |
| Dec 21, 2021 | US Army Corps of Engineers Approval Received |
| Jan 06, 2022 | Public Notice End Date |
| Jan 31, 2022 | Public Notice End Date Extension Granted |
| Feb 24, 2022 | Comments Received |
| Feb 28, 2022 | Comments Received |
| Feb 28, 2022 | Public Notice End Date Extension Granted |
| May 06, 2022 | Dock/1.1.6 Review approval |
| May 12, 2022 | Engineering Report |
| May 13, 2022 | Permit Approved |
| May 16, 2022 | Executive Sign Off |
| May 16, 2022 | Sent to Photo Copy |
| May 16, 2022 | Permit Mailed |
| Jun 01, 2022 | Land Evidence Date |