| Action Date | Action Description |
|---|---|
| Legal Response/Decision | |
| Jan 27, 2022 | Assent Application Received |
| Jan 31, 2022 | Administrative Review for Completeness |
| Feb 09, 2022 | Bio Team Review for Completeness |
| Feb 09, 2022 | Eng Team Review for Completeness |
| Feb 09, 2022 | Application Accepted |
| Feb 09, 2022 | Project Manager |
| Mar 10, 2022 | HPHC Review Pending |
| Mar 10, 2022 | HPHC Historical Preservation No Effect |
| Mar 18, 2022 | Additional Information Requested from Applicant |
| May 19, 2022 | Additional Information Requested from Applicant |
| Jun 13, 2022 | Correspondence Received |
| Aug 18, 2022 | 30-Day Notification of Cancellation letter |
| Oct 25, 2022 | Additional Information Received |
| Jul 05, 2023 | Additional Information Received |
| Jul 11, 2023 | 30 day Public Notice Issued |
| Aug 11, 2023 | Public Notice End Date |
| Sep 26, 2023 | Additional Information Requested from Applicant |
| Dec 05, 2023 | 30-Day Notification of Cancellation letter |
| Dec 21, 2023 | Plans Received |
| Mar 08, 2024 | Additional Information Requested from Applicant |
| Jun 13, 2024 | Correspondence Mailed/Faxed/E-mailed |
| Jun 13, 2024 | Correspondence Received |
| Jun 17, 2024 | Additional Information Received |
| Nov 29, 2024 | Stipulation Package from Biologist |
| Nov 29, 2024 | Stipulation Package by Engineer |
| Nov 29, 2024 | Biologist Report |
| Nov 29, 2024 | Engineering Report |
| Dec 03, 2024 | Executive Signoff of Staff Reports |
| Dec 10, 2024 | Council Approval Granted |
| Jul 25, 2025 | Typist for Processing |
| Jul 25, 2025 | Executive Sign Off |
| Jul 25, 2025 | Permit Approved |
| Jul 28, 2025 | Permit Mailed |
| Aug 05, 2025 | Land Evidence Date |