| Action Date | Action Description |
|---|---|
| Jan 28, 2022 | Assent Application Received |
| Feb 01, 2022 | Administrative Review for Completeness |
| Feb 01, 2022 | CHA Worksheet received |
| Feb 07, 2022 | Bio Team Review for Completeness |
| Feb 07, 2022 | Deficient Application - Owner Notification Sent |
| Mar 14, 2022 | Deficiency Response Received |
| Mar 24, 2022 | Bio Team Review for Completeness |
| Mar 24, 2022 | Application Accepted |
| Mar 24, 2022 | Project Manager |
| Apr 18, 2022 | HPHC Historical Preservation No Effect |
| Jun 03, 2022 | Biologist Report |
| Jun 14, 2022 | Typist for Processing |
| Jun 14, 2022 | Executive Sign Off |
| Jun 14, 2022 | Sent to Photo Copy |
| Jun 14, 2022 | Permit Approved |
| Jun 14, 2022 | Permit Mailed |
| Jul 12, 2022 | Land Evidence Date |