| Action Date | Action Description |
|---|---|
| Aug 05, 2022 | Maintenance Certification Request |
| Aug 11, 2022 | Administrative Review for Completeness |
| Aug 25, 2022 | Eng Team Review for Completeness |
| Aug 25, 2022 | Deficient Application - Owner Notification Sent |
| Aug 30, 2022 | Deficient Application Picked Up |
| Nov 04, 2022 | Deficiency Response Received |
| Nov 16, 2022 | Eng Team Review for Completeness |
| Nov 16, 2022 | Application Accepted |
| Nov 16, 2022 | Project Manager |
| Dec 07, 2022 | Engineering Report |
| Dec 20, 2022 | HPHC Historical Preservation No Effect |
| Jan 10, 2023 | Typist for Processing |
| Jan 10, 2023 | Executive Sign Off |
| Jan 10, 2023 | Sent to Photo Copy |
| Jan 10, 2023 | Permit Approved |
| Jan 12, 2023 | Permit Mailed |
| May 28, 2025 | Additional Information Received |