| Action Date | Action Description |
|---|---|
| Aug 24, 2022 | Maintenance Certification Request |
| Aug 25, 2022 | Administrative Review for Completeness |
| Sep 08, 2022 | Eng Team Review for Completeness |
| Sep 20, 2022 | Deficient Application - Owner Notification Sent |
| Jan 11, 2023 | Deficiency Response Received |
| Jan 23, 2023 | Eng Team Review for Completeness |
| Jan 23, 2023 | Application Accepted |
| Jan 23, 2023 | Project Manager |
| Jan 27, 2023 | HPHC Historical Preservation No Effect |
| Feb 13, 2023 | Engineering Report |
| Feb 27, 2023 | Typist for Processing |
| Feb 27, 2023 | Executive Sign Off |
| Feb 27, 2023 | Sent to Photo Copy |
| Feb 27, 2023 | Permit Approved |
| Feb 28, 2023 | Permit Mailed |
| Mar 22, 2023 | Land Evidence Date |
| Sep 15, 2023 | Commencement of Work Notice received |