| Action Date | Action Description |
|---|---|
| Nov 01, 2022 | HPHC Historical Preservation No Effect |
| Nov 01, 2022 | Dredge Application |
| Nov 03, 2022 | Administrative Review for Completeness |
| Dec 06, 2022 | Eng Team Review for Completeness |
| Dec 06, 2022 | Application Accepted |
| Dec 06, 2022 | Project Manager |
| Jan 18, 2023 | Joint Public Notice |
| Feb 03, 2023 | HPHC Historical Preservation No Effect |
| Feb 13, 2023 | Objections/Comments Received |
| Feb 14, 2023 | Objections/Comments Received |
| Feb 17, 2023 | Objections/Comments Received |
| Feb 17, 2023 | Objections/Comments Received |
| Feb 17, 2023 | Letter of Support for Project |
| Feb 18, 2023 | Public Notice End Date |
| Feb 20, 2023 | Objections/Comments Received |
| Mar 17, 2023 | Correspondence Received |
| Jul 26, 2023 | Plans Received |
| Aug 15, 2023 | Objections/Comments Received |
| Aug 24, 2023 | Comments Received |
| Nov 17, 2023 | Comments Received |
| Jul 29, 2024 | Mail Agenda Notice |
| Aug 15, 2024 | Entry of Appearance Received |
| Aug 20, 2024 | Executive Signoff of Staff Reports |
| Aug 20, 2024 | Engineering Report |
| Aug 26, 2024 | Correspondence Received |
| Aug 27, 2024 | Semi-Monthly Meeting Date Scheduled |
| Aug 27, 2024 | Council Approval Granted |
| Sep 04, 2024 | Comments Received |
| Sep 05, 2024 | Correspondence Received |
| Oct 29, 2024 | 30 Day Appeal Notification to Owner |
| Oct 29, 2024 | Legal Response/Decision |
| Dec 03, 2024 | Stipulation Package by Engineer |
| Dec 03, 2024 | Permit Approved |
| Dec 06, 2024 | Permit Mailed |
| Dec 18, 2024 | Land Evidence Date |
| Feb 26, 2025 | Modification Request |
| Mar 03, 2025 | Administrative Review for Completeness |
| Mar 10, 2025 | Eng Team Review for Completeness |
| Mar 10, 2025 | Project Manager |
| Mar 10, 2025 | Application Accepted |
| Mar 18, 2025 | Correspondence Received |
| Mar 20, 2025 | Additional Information Received |
| Apr 07, 2025 | Additional Information Received |
| Apr 07, 2025 | Engineering Report |
| Apr 10, 2025 | HPHC Historical Preservation No Effect |
| Apr 21, 2025 | Modification Approved |
| Apr 21, 2025 | Modification mailed |
| May 16, 2025 | Commencement of Work Notice received |