| Action Date | Action Description | 
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| May 15, 2025 | Assent Application Received | 
| May 20, 2025 | Administrative Review for Completeness | 
| May 23, 2025 | Bio Team Review for Completeness | 
| May 23, 2025 | Application Accepted | 
| May 23, 2025 | Project Manager | 
| May 23, 2025 | Category A* (Docks) | 
| Jun 10, 2025 | Correspondence Received | 
| Jun 10, 2025 | Plans Received | 
| Jun 13, 2025 | HPHC Historical Preservation No Effect | 
| Jul 07, 2025 | 30 day Public Notice Issued | 
| Jul 16, 2025 | Dock Meeting -- Approval | 
| Aug 07, 2025 | Public Notice End Date | 
| Aug 08, 2025 | Biologist Report | 
| Aug 18, 2025 | Typist for Processing | 
| Aug 18, 2025 | Executive Sign Off | 
| Aug 18, 2025 | Sent to Photo Copy | 
| Aug 18, 2025 | Permit Approved | 
| Aug 21, 2025 | Permit Mailed | 
| Aug 25, 2025 | Land Evidence Date |