| Action Date | Action Description |
|---|---|
| Violation Exists on this Site (NOV) | |
| Monitoring Report | |
| Jan 28, 2005 | Assent Application Received |
| Jan 31, 2005 | Administrative Review for Completeness |
| Feb 01, 2005 | Team Review for Completeness |
| Feb 01, 2005 | Application Accepted |
| Feb 01, 2005 | Category B assigned |
| Feb 23, 2005 | Additional Information Received |
| Feb 25, 2005 | 30 day Public Notice Issued |
| Mar 03, 2005 | Additional Information Received |
| Mar 26, 2005 | Public Notice End Date |
| Mar 31, 2005 | Correspondence Received |
| Apr 01, 2005 | Correspondence Received |
| Apr 08, 2005 | Executive Sign Off |
| Apr 08, 2005 | Engineering Report |
| Apr 08, 2005 | Biologist Report |
| Apr 20, 2005 | Correspondence Received |
| Apr 26, 2005 | Semi-Monthly Meeting Held |
| Apr 26, 2005 | Council Approval Granted |
| Apr 26, 2005 | Permit Approved |
| Apr 29, 2005 | Stipulation Package from Biologist |
| May 02, 2005 | Typist for Processing |
| May 02, 2005 | Executive Sign Off |
| May 03, 2005 | Sent to Photo Copy |
| May 04, 2005 | Engineering Report |
| May 05, 2005 | Executive Sign Off |
| May 05, 2005 | Land Evidence Date |
| May 05, 2005 | Legal Response/Decision |
| Mar 16, 2007 | Modification Request |
| Mar 19, 2007 | Administrative Review for Completeness |
| Mar 20, 2007 | Team Review for Completeness |
| Mar 20, 2007 | Team Review for Completeness |
| Mar 22, 2007 | Biologist Report |
| Mar 22, 2007 | Engineering Report |
| Mar 26, 2007 | Typist for Processing |
| Mar 29, 2007 | Executive Sign Off |
| Mar 29, 2007 | Sent to Photo Copy |
| Mar 29, 2007 | Modification Approved |
| Apr 04, 2007 | Land Evidence Date |
| Aug 31, 2007 | Modification Request |
| Sep 07, 2007 | Administrative Review for Completeness |
| Sep 10, 2007 | Team Review for Completeness |
| Sep 10, 2007 | Team Review for Completeness |
| Sep 21, 2007 | HPHC Historical Preservation No Effect |
| Oct 24, 2007 | Additional Information Requested from Applicant |
| Nov 15, 2007 | Application Cancelled |
| Nov 19, 2007 | Certified Receipt Received |
| Dec 11, 2007 | Additional Information Received |
| Dec 19, 2007 | Extension of Permit Request |
| Dec 19, 2007 | Correspondence Mailed/Faxed/E-mailed |
| Jan 04, 2008 | Modification Request |
| Jan 07, 2008 | Administrative Review for Completeness |
| Jan 07, 2008 | Team Review for Completeness |
| Jan 16, 2008 | Biologist Report |
| Jan 16, 2008 | Engineering Report |
| Jan 16, 2008 | Typist for Processing |
| Jan 16, 2008 | Executive Sign Off |
| Jan 16, 2008 | Sent to Photo Copy |
| Jan 16, 2008 | Modification Approved |
| Feb 04, 2008 | HPHC Historical Preservation No Effect |
| Feb 05, 2008 | Land Evidence Date |
| Mar 10, 2008 | Correspondence Received |
| Mar 18, 2008 | Correspondence Mailed/Faxed/E-mailed |
| Mar 18, 2008 | Correspondence Mailed/Faxed/E-mailed |
| Mar 24, 2008 | Plans Received |
| Mar 24, 2008 | Enforcement Compliance Inspection Required |
| Mar 27, 2008 | Process Extension |
| Mar 27, 2008 | Interim Approval Granted |
| Apr 15, 2008 | Letter of Authorization |
| Jan 28, 2009 | Extension of Permit Request |
| Feb 13, 2009 | Monitoring Report |
| Oct 21, 2009 | Enforcement Compliance Inspection Required |
| Oct 21, 2009 | Process Extension |
| Oct 21, 2009 | Extension Approved |
| Jan 14, 2014 | Monitoring Report |
| Sep 08, 2014 | Monitoring Report |