| Action Date | Action Description |
|---|---|
| Mar 03, 2005 | Assent Application Received |
| Mar 04, 2005 | Administrative Review for Completeness |
| Mar 04, 2005 | Plans Received |
| Mar 07, 2005 | Application Accepted |
| Mar 07, 2005 | Team Review for Completeness |
| Mar 29, 2005 | Historical Preservation Approval Granted |
| May 11, 2005 | Biologist Report |
| May 12, 2005 | Typist for Processing |
| May 12, 2005 | Executive Sign Off |
| May 12, 2005 | Sent to Photo Copy |
| May 12, 2005 | Permit Approved |
| Jul 22, 2005 | Land Evidence Date |
| Apr 09, 2008 | Extension of Permit Request |
| Apr 30, 2008 | Enforcement Compliance Inspection Required |
| May 01, 2008 | Process Extension |
| May 01, 2008 | Typist for Processing |
| May 01, 2008 | Executive Sign Off |
| May 01, 2008 | Extension Approved |