| Action Date | Action Description |
|---|---|
| Apr 13, 2005 | Assent Application Received |
| Apr 14, 2005 | Administrative Review for Completeness |
| Apr 14, 2005 | Team Review for Completeness |
| Apr 14, 2005 | Application Accepted |
| Apr 15, 2005 | Category B assigned |
| May 03, 2005 | HPHC Review Pending |
| May 16, 2005 | Biologist Report |
| May 16, 2005 | Engineering Report |
| May 16, 2005 | 30 day Public Notice Issued |
| May 16, 2005 | Executive Sign Off |
| May 26, 2005 | Supervisor Biologist SignOff |
| May 26, 2005 | Supervisor Engineer SignOff |
| Jun 02, 2005 | Executive Sign Off |
| Jun 02, 2005 | Mail Agenda Notice |
| Jun 14, 2005 | Semi-Monthly Meeting Date Scheduled |
| Jun 14, 2005 | Correspondence Received |
| Jun 14, 2005 | Correspondence Received |
| Jun 14, 2005 | Council Approval Granted |
| Jun 16, 2005 | Public Notice End Date |
| Jul 08, 2005 | Correspondence Received |
| Sep 16, 2005 | Biologist Report |
| Sep 16, 2005 | Typist for Processing |
| Sep 16, 2005 | Permit Approved |
| Sep 16, 2005 | Stipulation Package from Biologist |
| Sep 16, 2005 | Stipulation Package by Engineer |
| Sep 19, 2005 | Legal Response/Decision |
| Sep 19, 2005 | Executive Sign Off |
| Sep 19, 2005 | Sent to Photo Copy |
| Sep 29, 2005 | Land Evidence Date |
| Apr 24, 2009 | Correspondence Mailed/Faxed/E-mailed |
| Aug 05, 2009 | Conservation Easement Mailed. |
| Aug 19, 2009 | Conservation Easement Recording received |