| Action Date | Action Description |
|---|---|
| Aug 23, 2005 | Assent Application Received |
| Aug 24, 2005 | Administrative Review for Completeness |
| Aug 29, 2005 | Deficient Application - Owner Notification Sent |
| Sep 07, 2005 | Deficient Application Picked Up |
| Oct 25, 2005 | Deficiency Response Received |
| Oct 27, 2005 | Team Review for Completeness |
| Oct 27, 2005 | Application Accepted |
| Nov 21, 2005 | HPHC Historical Preservation No Effect |
| Dec 13, 2005 | Typist for Processing |
| Dec 13, 2005 | Executive Sign Off |
| Dec 13, 2005 | Sent to Photo Copy |
| Dec 13, 2005 | Permit Approved |
| Dec 13, 2005 | Biologist Report |
| Dec 13, 2005 | Engineering Report |
| Jan 10, 2006 | Land Evidence Date |
| Sep 15, 2008 | Extension of Permit Request |
| Sep 19, 2008 | Enforcement Compliance Inspection Required |
| Sep 22, 2008 | Process Extension |
| Sep 22, 2008 | Extension Approved |