| Action Date | Action Description |
|---|---|
| Oct 11, 2005 | Assent Application Received |
| Oct 11, 2005 | Administrative Review for Completeness |
| Oct 17, 2005 | Team Review for Completeness |
| Oct 17, 2005 | Application Accepted |
| Oct 17, 2005 | Category B assigned |
| Oct 27, 2005 | 30 day Public Notice Issued |
| Nov 03, 2005 | HPHC Historical Preservation No Effect |
| Nov 27, 2005 | Public Notice End Date |
| Jul 17, 2006 | Biologist Report |
| Jul 17, 2006 | Engineering Report |
| Jul 18, 2006 | Executive Sign Off |
| Aug 11, 2006 | Ready to Schedule Semi-Monthly Meeting |
| Aug 11, 2006 | Mail Agenda Notice |
| Aug 22, 2006 | Semi-Monthly Meeting Date Scheduled |
| Aug 25, 2006 | Mail Agenda Notice |
| Aug 25, 2006 | Ready to Schedule Semi-Monthly Meeting |
| Aug 31, 2006 | Water Quality Certification |
| Sep 12, 2006 | Semi-Monthly Meeting Postponed |
| Sep 12, 2006 | Semi-Monthly Meeting Date Scheduled |
| Sep 19, 2006 | Semi-Monthly Meeting Held |
| Sep 19, 2006 | Ready to Schedule Semi-Monthly Meeting |
| Sep 19, 2006 | Council Approval Granted |
| Sep 26, 2006 | Stipulation Package from Biologist |
| Sep 26, 2006 | Stipulation Package by Engineer |
| Sep 26, 2006 | Typist for Processing |
| Sep 26, 2006 | Executive Sign Off |
| Sep 26, 2006 | Sent to Photo Copy |
| Sep 26, 2006 | Permit Approved |
| Oct 11, 2006 | Land Evidence Date |
| Oct 25, 2006 | Legal Response/Decision |
| May 21, 2009 | Correspondence Received |
| May 22, 2009 | Extension of Permit Request |
| Jun 09, 2009 | Letter of Authorization |
| Jun 18, 2009 | Commencement of Work Notice received |
| Oct 15, 2009 | Process Extension |
| Oct 15, 2009 | Extension Approved |
| Oct 15, 2009 | Enforcement Compliance Inspection Required |