| Action Date | Action Description |
|---|---|
| Nov 07, 2005 | Assent Application Received |
| Nov 08, 2005 | Administrative Review for Completeness |
| Nov 21, 2005 | Deficient Application - Owner Notification Sent |
| Dec 23, 2005 | Deficiency Response Received |
| Jan 10, 2006 | Deficient Application - Owner Notification Sent |
| Mar 17, 2006 | Deficiency Response Received |
| Mar 24, 2006 | Team Review for Completeness |
| Mar 24, 2006 | Application Accepted |
| Mar 24, 2006 | Category B assigned |
| Apr 03, 2006 | HPHC Historical Preservation No Effect |
| Apr 06, 2006 | 30 day Public Notice Issued |
| May 11, 2006 | Additional Information Received |
| Jun 16, 2006 | Correspondence Received |
| Jun 19, 2006 | Public Notice End Date |
| Oct 17, 2006 | Plans Received |
| Nov 28, 2006 | Biologist Report |
| Nov 28, 2006 | Engineering Report |
| Nov 29, 2006 | Supervisor Engineer SignOff |
| Nov 29, 2006 | Supervisor Biologist SignOff |
| Nov 30, 2006 | Executive Sign Off |
| Dec 04, 2006 | US Army Corp of Engineers Permit Date |
| Dec 07, 2006 | US Army Corps of Engineers Approval Received |
| Jan 26, 2007 | Typist for Processing |
| Jan 26, 2007 | Executive Sign Off |
| Jan 26, 2007 | Sent to Photo Copy |
| Jan 26, 2007 | Permit Approved |
| Jun 07, 2007 | Land Evidence Date |
| Jun 18, 2007 | Commencement of Work Notice received |