| Action Date | Action Description |
|---|---|
| Jan 17, 2006 | Assent Application Received |
| Jan 17, 2006 | Administrative Review for Completeness |
| Jan 25, 2006 | Deficient Application - Owner Notification Sent |
| Feb 13, 2006 | Deficiency Response Received |
| Feb 15, 2006 | Team Review for Completeness |
| Feb 15, 2006 | Category A* (Docks) |
| Mar 10, 2006 | 30 day Public Notice Issued |
| Mar 22, 2006 | Correspondence Received |
| May 01, 2006 | Correspondence Received |
| May 01, 2006 | Public Notice End Date |
| May 03, 2006 | Correspondence Received |
| May 11, 2006 | Biologist Report |
| May 11, 2006 | Engineering Report |
| May 23, 2006 | US Army Corp of Engineers Permit Date |
| May 25, 2006 | US Army Corps of Engineers Approval Received |
| Oct 31, 2006 | Supervisor Biologist SignOff |
| Oct 31, 2006 | Supervisor Engineer SignOff |
| Nov 02, 2006 | Executive Sign Off |
| Jan 22, 2007 | Typist for Processing |
| Jan 22, 2007 | Executive Sign Off |
| Jan 22, 2007 | Sent to Photo Copy |
| Jan 22, 2007 | Permit Approved |
| Feb 07, 2007 | Land Evidence Date |
| May 10, 2007 | Commencement of Work Notice received |