| Action Date | Action Description |
|---|---|
| Feb 13, 2008 | Assent Application Received |
| Feb 14, 2008 | Administrative Review for Completeness |
| Feb 20, 2008 | Team Review for Completeness |
| Feb 20, 2008 | Team Review for Completeness |
| Feb 20, 2008 | Application Accepted |
| Feb 20, 2008 | Category A* (Docks) |
| Mar 11, 2008 | HPHC Historical Preservation No Effect |
| Apr 04, 2008 | Additional Information Received |
| Apr 21, 2008 | 30 day Public Notice Issued |
| May 21, 2008 | Public Notice End Date |
| Jun 23, 2008 | Dock Meeting -- Approval |
| Jun 26, 2008 | Typist for Processing |
| Jun 26, 2008 | Executive Sign Off |
| Jun 26, 2008 | Sent to Photo Copy |
| Jun 26, 2008 | Permit Approved |
| Jun 26, 2008 | Biologist Report |
| Jun 26, 2008 | Engineering Report |
| Jun 30, 2008 | US Army Corp of Engineers Permit Date |
| Jul 03, 2008 | US Army Corps of Engineers Approval Received |
| Jul 09, 2008 | Land Evidence Date |
| Jul 11, 2008 | Commencement of Work Notice received |