| Action Date | Action Description |
|---|---|
| Jun 29, 2009 | Assent Application Received |
| Jun 29, 2009 | Administrative Review for Completeness |
| Jun 30, 2009 | Team Review for Completeness |
| Jun 30, 2009 | Team Review for Completeness |
| Aug 05, 2009 | Application Accepted |
| Aug 18, 2009 | HPHC Historical Preservation No Effect |
| Sep 29, 2009 | Typist for Processing |
| Sep 29, 2009 | Biologist Report |
| Sep 29, 2009 | Permit Approved |
| Sep 30, 2009 | Executive Sign Off |
| Oct 01, 2009 | Sent to Photo Copy |
| Aug 10, 2012 | Extension Toll letter mailed |
| Aug 22, 2013 | Commencement of Work Notice received |
| May 11, 2016 | Additional Information Requested from Applicant |