| Action Date | Action Description |
|---|---|
| Aug 03, 2009 | Preliminary Determination Request (Coastal) |
| Aug 04, 2009 | Administrative Review for Completeness |
| Aug 05, 2009 | Team Review for Completeness |
| Aug 05, 2009 | Team Review for Completeness |
| Aug 11, 2009 | Assent Application Received |
| Aug 11, 2009 | Administrative Review for Completeness |
| Aug 11, 2009 | Team Review for Completeness |
| Aug 11, 2009 | Team Review for Completeness |
| Aug 11, 2009 | Application Accepted |
| Aug 11, 2009 | Category A assigned |
| Aug 12, 2009 | Biologist Report |
| Aug 12, 2009 | Engineering Report |
| Aug 13, 2009 | Typist for Processing |
| Aug 13, 2009 | Executive Sign Off |
| Aug 13, 2009 | Permit Approved |
| Aug 14, 2009 | Sent to Photo Copy |
| Aug 26, 2009 | Land Evidence Date |
| Aug 27, 2009 | HPHC Historical Preservation No Effect |
| Oct 15, 2009 | Commencement of Work Notice received |