| Action Date | Action Description |
|---|---|
| Dec 12, 2011 | Assent Application Received |
| Dec 13, 2011 | Administrative Review for Completeness |
| Dec 21, 2011 | Team Review for Completeness |
| Dec 21, 2011 | Team Review for Completeness |
| Dec 21, 2011 | Application Accepted |
| Dec 21, 2011 | Category B assigned |
| Jan 03, 2012 | 30 day Public Notice Issued |
| Jan 04, 2012 | HPHC Historical Preservation No Effect |
| Jan 26, 2012 | Additional Information Received |
| Jan 27, 2012 | Biologist Report |
| Feb 03, 2012 | Public Notice End Date Extension Granted |
| Feb 03, 2012 | Public Notice End Date |
| Feb 07, 2012 | Engineering Report |
| Feb 09, 2012 | Typist for Processing |
| Feb 09, 2012 | Category A assigned |
| Feb 09, 2012 | Permit Approved |
| Feb 15, 2012 | Executive Sign Off |
| Feb 15, 2012 | Sent to Photo Copy |
| Feb 21, 2012 | Land Evidence Date |
| Mar 06, 2012 | Correspondence Received |
| Apr 02, 2012 | Water Quality Certification |
| Apr 05, 2012 | Commencement of Work Notice received |
| May 09, 2012 | Additional Information Received |
| May 10, 2012 | Correspondence Mailed/Faxed/E-mailed |
| Jan 23, 2013 | Correspondence Received |