| Action Date | Action Description |
|---|---|
| Jun 18, 2013 | Assent Application Received |
| Jun 19, 2013 | Administrative Review for Completeness |
| Jul 08, 2013 | Team Review for Completeness |
| Jul 08, 2013 | Team Review for Completeness |
| Jul 08, 2013 | Application Accepted |
| Jul 09, 2013 | 30 day Public Notice Issued |
| Jul 22, 2013 | Objections/Comments Received |
| Jul 23, 2013 | Historical Preservation Conditional Approval |
| Jul 24, 2013 | Public Notice End Date |
| Aug 02, 2013 | Additional Information Received |
| Aug 08, 2013 | Interim Approval Granted |
| Aug 09, 2013 | Additional Information Received |
| Apr 10, 2014 | Correspondence Received |
| Feb 18, 2015 | Plans Received |
| May 20, 2015 | Correspondence Received |
| Jun 19, 2015 | Correspondence Received |
| Jul 02, 2015 | Plans Received |
| Aug 03, 2015 | Interim Approval Granted |
| Sep 03, 2015 | Water Quality Certification |
| Sep 18, 2015 | Engineering Report |
| Sep 18, 2015 | Additional Information Requested from Applicant |
| Sep 21, 2015 | Correspondence Received |
| Oct 13, 2015 | Correspondence Received |
| Oct 27, 2015 | HPHC Historical Preservation No Effect |
| Nov 05, 2015 | Plans Received |
| Nov 18, 2015 | Additional Information Received |
| Nov 19, 2015 | Biologist Report |
| Nov 20, 2015 | Typist for Processing |
| Nov 20, 2015 | Executive Sign Off |
| Nov 20, 2015 | Sent to Photo Copy |
| Nov 20, 2015 | Permit Approved |
| Nov 24, 2015 | Additional Information Received |
| Mar 14, 2016 | Modification Request |
| Mar 16, 2016 | Administrative Review for Completeness |
| Mar 17, 2016 | Team Review for Completeness |
| Mar 17, 2016 | Team Review for Completeness |
| Mar 30, 2016 | HPHC Historical Preservation No Effect |
| Mar 31, 2016 | Additional Information Received |
| Apr 15, 2016 | Modification Request |
| Apr 15, 2016 | Plans Received |
| Apr 18, 2016 | Administrative Review for Completeness |
| Apr 22, 2016 | Plans Received |
| Apr 27, 2016 | Modification Withdrawn |
| May 16, 2016 | Typist for Processing |
| May 16, 2016 | Executive Sign Off |
| May 16, 2016 | Sent to Photo Copy |
| May 16, 2016 | Modification Approved |
| May 16, 2016 | Biologist Report |
| May 16, 2016 | Engineering Report |
| May 20, 2016 | Additional Information Received |
| Jun 19, 2018 | Correspondence Received |
| May 20, 2019 | Correspondence Received |
| Jun 19, 2019 | Modification Request |
| Jun 21, 2019 | Administrative Review for Completeness |
| Jul 19, 2019 | Team Review for Completeness |
| Jul 19, 2019 | Application Accepted |
| Aug 19, 2019 | Additional Information Received |
| Aug 22, 2019 | HPHC Review Pending |
| Aug 22, 2019 | HPHC Historical Preservation No Effect |
| Sep 17, 2019 | Additional Information Received |
| Sep 20, 2019 | Additional Information Received |
| Sep 30, 2019 | Additional Information Received |
| Oct 04, 2019 | Additional Information Received |
| Oct 04, 2019 | Extension of Permit Request |
| Oct 09, 2019 | Additional Information Received |
| Oct 11, 2019 | Biologist Report |
| Oct 15, 2019 | Typist for Processing |
| Oct 15, 2019 | Executive Sign Off |
| Oct 15, 2019 | Modification Approved |
| Oct 15, 2019 | Extension Approved |
| Nov 08, 2019 | Correspondence Received |
| Jan 10, 2020 | Extension of Permit Request |
| Jan 24, 2020 | Enforcement Compliance Inspection Required |
| Jan 24, 2020 | Process Extension |
| Jan 24, 2020 | Extension Approved |
| Oct 06, 2020 | Modification Request |
| Oct 06, 2020 | Administrative Review for Completeness |
| Oct 07, 2020 | Project Manager |
| Nov 19, 2020 | Policy Review |
| Nov 19, 2020 | Modification Approved |
| Dec 11, 2020 | Land Evidence Date |
| Dec 16, 2020 | Land Evidence Date |
| Jun 21, 2021 | Extension of Permit Request |
| Mar 17, 2022 | Enforcement Compliance Inspection Required |
| Mar 25, 2022 | Extension Approved |