| Action Date | Action Description |
|---|---|
| Aug 04, 2014 | Assent Application Received |
| Aug 04, 2014 | Administrative Review for Completeness |
| Aug 08, 2014 | Team Review for Completeness |
| Aug 08, 2014 | Application Accepted |
| Aug 08, 2014 | Category B assigned |
| Sep 04, 2014 | HPHC Historical Preservation No Effect |
| Oct 01, 2014 | 30 day Public Notice Issued |
| Oct 27, 2014 | Correspondence Received |
| Nov 01, 2014 | Public Notice End Date |
| Dec 17, 2014 | US Army Corps of Engineers Approval Received |
| Dec 24, 2014 | Engineering Report |
| Jan 15, 2015 | Mail Agenda Notice |
| Jan 22, 2015 | Continued application |
| Feb 03, 2015 | Ready to Schedule Semi-Monthly Meeting |
| Feb 10, 2015 | Semi-Monthly Meeting Date Scheduled |
| Feb 11, 2015 | Continued application |
| Feb 23, 2015 | Correspondence Received |
| Mar 13, 2015 | Ready to Schedule Semi-Monthly Meeting |
| Mar 13, 2015 | Mail Agenda Notice |
| Mar 16, 2015 | Correspondence Received |
| Mar 24, 2015 | Council Approval Granted |
| Mar 24, 2015 | Semi-Monthly Meeting Date Scheduled |
| May 27, 2015 | 30 Day Appeal Notification to Owner |
| May 27, 2015 | Legal Response/Decision |
| May 29, 2015 | Stipulation Package by Engineer |
| Jun 02, 2015 | Typist for Processing |
| Jun 02, 2015 | Permit Approved |
| Jun 04, 2015 | Executive Sign Off |
| Jun 04, 2015 | Sent to Photo Copy |
| Jun 08, 2015 | Land Evidence Date |
| Oct 20, 2015 | Commencement of Work Notice received |