| Action Date | Action Description |
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Nov 13, 2020 | Assent Application Received |
| Nov 17, 2020 | Administrative Review for Completeness |
| Nov 24, 2020 | Bio Team Review for Completeness |
| Nov 24, 2020 | Application Accepted |
| Nov 24, 2020 | Project Manager |
| Nov 25, 2020 | Category A* (Docks) |
| Dec 14, 2020 | 30 day Public Notice Issued |
| Jan 12, 2021 | Objections/Comments Received |
| Jan 13, 2021 | HPHC Historical Preservation No Effect |
| Jan 13, 2021 | HPHC Review Pending |
| Jan 14, 2021 | Public Notice End Date |
| Apr 26, 2021 | Correspondence Received |
| Jun 28, 2021 | Additional Information Received |
| Oct 13, 2021 | Additional Information Received |
| Nov 04, 2021 | Typist for Processing |
| Nov 04, 2021 | Permit Approved |
| Nov 04, 2021 | Engineering Report |
| Nov 05, 2021 | Permit Mailed |
| Nov 05, 2021 | Executive Sign Off |
| Nov 15, 2021 | Land Evidence Date |