| Action Date | Action Description |
|---|---|
| Jul 22, 2021 | Assent Application Received |
| Jul 27, 2021 | Administrative Review for Completeness |
| Jul 27, 2021 | CHA Worksheet received |
| Jul 29, 2021 | Bio Team Review for Completeness |
| Jul 29, 2021 | Deficient Application - Owner Notification Sent |
| Nov 02, 2021 | Deficient Application Picked Up |
| Jan 10, 2022 | Deficiency Response Received |
| Jan 20, 2022 | Bio Team Review for Completeness |
| Jan 20, 2022 | Application Accepted |
| Jan 20, 2022 | Project Manager |
| Jan 31, 2022 | Additional Information Requested from Applicant |
| Feb 16, 2022 | HPHC Historical Preservation Comments/Concerns |
| Feb 16, 2022 | HPHC Review Pending |
| Mar 17, 2022 | Correspondence Received |
| Mar 17, 2022 | Correspondence Mailed/Faxed/E-mailed |
| Mar 22, 2022 | HPHC Historical Preservation No Effect |
| Apr 27, 2022 | Permit Approved |
| Apr 27, 2022 | Permit Mailed |
| Apr 27, 2022 | Typist for Processing |
| Apr 27, 2022 | Biologist Report |
| Apr 27, 2022 | Engineering Report |
| Apr 29, 2022 | Permit Mailed |
| Jan 12, 2023 | Land Evidence Date |