| Action Date | Action Description |
|---|---|
| Mar 14, 2022 | Assent Application Received |
| Mar 21, 2022 | Administrative Review for Completeness |
| Mar 22, 2022 | Eng Team Review for Completeness |
| Mar 22, 2022 | Bio Team Review for Completeness |
| Mar 22, 2022 | Application Accepted |
| Mar 22, 2022 | Project Manager |
| Apr 20, 2022 | HPHC Review Pending |
| Apr 20, 2022 | HPHC Historical Preservation No Effect |
| Apr 27, 2022 | Additional Information Requested from Applicant |
| Jun 21, 2022 | Correspondence Received |
| Jun 23, 2022 | Plans Received |
| Jun 28, 2022 | Engineering Report |
| Jun 28, 2022 | Biologist Report |
| Jul 05, 2022 | Permit Mailed |
| Jul 05, 2022 | Typist for Processing |
| Jul 05, 2022 | Executive Sign Off |
| Jul 05, 2022 | Sent to Photo Copy |
| Jul 05, 2022 | Permit Approved |
| Aug 08, 2022 | Land Evidence Date |